Inspection Regulations
Scheduling Inspections:
Building Inspections FOUNDATION: After damproofing, and the installation of all exterior insulation and foundation drains are in place, and before any backfilling occurs. FRAMING: After all rough electrical, plumbing and heating is approved and the roof is weather resistant. INSULATION: After all insulation, wind wash, and vapor barriers are in place, and the roof is weather proof. WALLBOARD: After all wallboard is installed and before joints and fasteners are taped and finished.
FINAL: After all final electrical, plumbing and heating is approved,
the building is completed, and before occupancy. A Certificate of
Occupancy for new buildings will be issued when all inspections have been approved and
the inspection record is returned to the Building Department. UNDERGROUND: If applicable, when all work is complete and will stand the required tests, and before covering. ROUGH: After all above grade work is complete and will stand the required tests, and before covering.
FINAL: After all fixtures are set and the completed system will stand the
required tests. ROUGH: After all above grade work is complete and before covering.
FUEL GAS PIPING: After all piping materials have been approved and tested, and before covering. ROUGH: After all above grade work is complete and before covering.
FINAL: After all fixtures are set and the completed system will stand the required tests. FIREPLACE ROUGH: After unit is installed, gas piping is into appliance, and flue and vent terminations are complete.
FIREPLACE FINAL: After all hearths, facing materials, and mantels are complete.